Temple Construction Updates

August - 2025

Highlights:

1.⁠ ⁠Boundary Wall : Iron fabrication work is in progress. Despite delays due to rains and festivals, the West side is near completion, and other sides have started.
2.⁠ Radha Krishna Temple Site (East): Stones are mostly cleared. Area prepared for Kitchen construction in Phase 1, which will serve as the temporary temple.
3.⁠ ⁠Pancha Tattva Block (West): Stone blasting completed; shifting of stones is in progress.
4.⁠ ⁠Seva Office (South): Pillars erected for ready-made container. This will house the Seva Office to serve devotees with donation receipts, drawings, and meeting space.
5.⁠ ⁠Temple Drawings: Work is ongoing with Stapathi Prasad Garu, Architect Kiran Prabhu, under the guidance of HH Bhakti Padma Swami Maharaj.
6.⁠ ⁠Temple Lease: Extension to 22 years approved by the Minister.

 